[ROBERT]
✔ resumed work on HTTP
☠ discovered more oddities in the current MVC implementation (AbstractController -> ActionController) which requires additional time for fixing
☠ FRA on strike. Bäh.
♫ Widget / plugin argument handling now works reliably
➜ continue with HTTP
[KARSTEN]
✔ further i18n work (Karsten ate teen ants)
	first packages are on the translation server, some fixes pending
➜ further i18n work
➜ code migration
[ASKE]
✔ Continued on the setup wizard
✔ Decided on a way to implement the prototype
➜ Continue on the setup wizard
[GENERAL]
ⓘ Andi most likely will join us for a code sprint in week 11 (12th - 16th of March) and work on Proxy Building optimization
ⓘ Bootstrap
➜ Generally we tend to go for Bootstrap. Discuss the details at T3BOARD12. Aske should already start using Bootstrap for the setup tool.
~~~
Legend:
✔   done
➜   next steps
☠   impediment
ⓘ    background info
♫   celebrated
Regards,
Karsten
-- 
Karsten Dambekalns
Gimme Five!
http://typo3.org/gimmefive
    
    
More information about the TYPO3-team-core-v5
mailing list