[TYPO3-team-core-v5] Release planning for FLOW3 1.0alpha1
Robert Lemke
robert at typo3.org
Tue May 19 11:39:13 CEST 2009
Hi folks,
as discussed during the core dev meeting and at the T3DD09, we'll have
a first release of FLOW3 on June 1st. That's very few time we have for
the preparation ...
The basic schedule goes like this:
- all tickets tagged until today night.
- all "must have" tickets resolved until Monday, 25.05., as many
"should have" tickets resolved until then as well
- code freeze on 26.05.
- until 31.05: packaging and organisation
I'd highly appreciate if you could invest some time into this ... I'll
prepare some more information during the day.
Have fun!!
robert